APG clamping machine process flow chart

 APG machine produce process 4 steps: 

-1., install mould on APG clamps →heat it up to 60°C→open mould, brush mould release agent →close mould

-2, pre-mixing casting compound in vacuum pot →turn off vacuum valve when vacuum gage show -0.1→release vacuum, push vacuum pot nearby APG machine→

-3, APG Add pressure into vacuum pot and start injecting cast compound into mold, release pressure →open mold →take out products

-4 ,Curing. Move product in to oven.